Bayou Steel Orders Ladle System
Bayou Steel Corp. has issued an order to Danieli
Corp. for the turnkey supply of an 83-ton capacity ladle metallurgical facility.
The facility will be installed in the existing meltshop at Bayou Steel. The
supply includes the ladle furnace equipment and control system, all platforms
and foundations and a baghouse system. Construction engineering is being
supplied by Continental Design and Management Group, Inc. and construction
services are being provided by McIntosh Mechanical, Inc. The facility will be
operational in April 1999. The project is being handled jointly by Danieli
ControMet USA and Danieli Automation USA.