MINING UPDATE

 

MAY 2015

 

Mcilvaine Company

 

AMERICAS

Nevada Copper Focuses on Pumpkin Hollow Development

Newmont Says Opening New Nevada Gold District

Final EIS Completed for Montanore Project, Montana

Imperial Metals Starts Up at Red Chris Copper Mine in BC

Dynacor Receives Construction Permit for New Gold Mill in Peru

Yamana Gives Go-ahead for High-grade Cerro Moro Mine, Argentina

Endeavour Silver Increasing Production at El Cubo, Mexico

Outotec to Deliver Modular SX Technology to South America

EMEA

Boliden Expanding in Norway; Pursuing New Nickel Strategy for Finland

Work on Rio Tinto’s Spain Copper Project to Begin this Year

Russia’s Alrosa Launches Mining on the Botuobinskaya Pipe

Roxgold Clears Permitting for Yaramoko Gold Project

ASIA

Indian Coal Imports Could Surge This Year

India’s Largest Manganese Producer to Expand Production

Chinese Coal Industry Steps Into Production Control

AUSTRALIA/ OCEANIA

Australian Major Mining Construction Projects

Sirius Starts Construction of Nova Nickel Mine

Kintyre Uranium Project Receives Conditional Environmental Approval

 

AMERICAS

Nevada Copper Focuses on Pumpkin Hollow Development

Following passage on December 19, 2014, of a federal land bill conveying 10,400 acres of federal land to the city of Yerington, Nevada—land that will subsequently be conveyed to Nevada Copper—the company outlined updated plans to bring its Pumpkin Hollow copper project into production. Under the new land-ownership regime, the entire Pumpkin Hollow project area is being consolidated into a single, privately held land package owned by Nevada Copper, with all required permits under state jurisdiction.

 

Nevada Copper now expects to receive all key permits for open-pit operation at Pumpkin Hollow by June. All permits for underground operation are already in place.

 

With land-ownership issues settled, Nevada Copper has launched an integrated feasibility study to consider Pumpkin Hollow development as a single, large-scale, combined open-pit/underground project, with a single concentrator processing 70,000 short tons per day (st/d). The company had previously planned staged development of the project, with a high-grade underground mine and mill to be developed ahead of open-pit mining. Under the combined development plan, mill feed would include an average of 63,500 st/d of open-pit ore blended with 6,500 st/d of high-grade underground ore.

 

Nevada Copper anticipates that enhanced mill feed grades for the large mill, coupled with elimination of the capital required for the smaller 6,500-st/d mill proposed for the underground project, will provide better capital efficiency and overall better project economics.

 

Completion of the integrated feasibility study is targeted for April.

 

Nevada Copper President and CEO Giulio Bonifacio said, “We will continue to preserve our development options with respect to staged development versus a single, large, integrated project until such time as we have the results of the integrated feasibility study and can determine our optimal strategy going forward. In either case, first production is targeted for late 2016, early 2017, subject to completion of financing arrangements.”

 

Meanwhile, Nevada Copper is nearing completion of the circular, 24-ft-diameter, concrete-lined, production-sized shaft it is sinking to access Pumpkin Hollow’s underground deposits. As of February 10, the shaft was at the 1,806-ft level, more than 95% of the way toward the main 1,900-ft haulage level. After reaching the 1,900-ft level, about 700 ft of lateral development will begin on this level to establish setup locations for delineation and development drilling and to provide future access to the underground east ore zones. While this lateral development continues, the shaft will be deepened to its final depth of 2,160 ft.

 

An underground drill program totaling 26,000 ft is scheduled to start in May 2015. The program will focus on enlarging high-grade zones within the current reserve, especially in areas planned for mining in the early years, and will provide additional data for mine design while expanding open mineralized areas.

 

A Pumpkin Hollow open-pit drill program totaling 74,000 ft was already in progress as of mid-February.

Newmont Says Opening New Nevada Gold District

Denver-based Newmont Mining Corp is going ahead with building the first phase of its Long Canyon gold mine in Nevada, some 100 miles from the company's existing operations in the state.

 

The first phase, which consists of an open pit mine and heap leach operation, is expected to produce between 100,000 ounces and 150,000 ounces of gold a year over a mine life of 8 years.

 

First commercial production is expected in the first half of 2017 and costs are some of the best in the industry with all-in sustaining costs of between $500 and $600 per ounce.

 

Thanks to a phased approach to developing Long Canyon, Newmont has kept the capital outlay to between $250 million and $300 million, according to a company statement.

 

Newmont acquired the Long Canyon gold deposit from Fronteer Gold in April 2011.

 

The project will be funded through free cash flow and available cash balances, and leverage Newmont’s existing equipment, infrastructure and personnel. Capital expenditures will be allocated roughly equally in 2015 and 2016, with minimal spending in 2017. Project highlights include:

•High grade oxide ore processed by heap leaching

•Gold reserves of 1.2 million ounces at an average grade of 2.29 grams per tonneiii and highly prospective mineralization over a three mile strike length

•Estimated annual gold production of between 100,000 and 150,000 ounces over an eight year mine life for the first phase of operation

•Estimated average costs applicable to sales of between $400 and $500 per ounce and all-in sustaining costs of between $500 and $600 over the life of the mine; in the lowest cost quartile for gold production

•Leveraging 50 years’ experience operating in Nevada by relying on existing equipment, infrastructure and personnel

 

Federal and state permits necessary to proceed with development of the project have been secured following a 36-month study and public comment period. Once in operation, Long Canyon Phase 1 is expected to directly employ about 260 people. Newmont will continue to engage and partner with local and regional stakeholders throughout construction, operations and closure.

Final EIS Completed for Montanore Project, Montana

Mines Management, Inc. reported that the U.S. Forest Service has completed and issued the final Environmental Impact Statement (EIS) for the Montanore Project. Based on the agency’s analyses of issues considered throughout the review process, the USFS is also issuing a Draft Record of Decision (RoD) indicating its intent to authorize the project.

 

Completion of the final EIS and draft RoD signal commencement of the final phase of the permitting process for Montanore, which is located in northwestern Montana.

 

“The publication of the final EIS is the culmination of 10 years of technical and environmental analysis, including the completion and distribution of two draft EISs and significant public input, all of which has been incorporated into the project plan,” said Glenn M. Dobbs, chairman and CEO. “In light of the Montanore Project’s original approvals in 1993, we are gratified the project is nearing conclusion of a prolonged process in which significant improvements have been made to the project’s environmental footprint, including mitigation to protect important water resources, wildlife and habitat. Development and operation of the Montanore mine will result in enhancements to habitat and wetlands which otherwise would be impossible in the absence of the project and which will contribute to, and protect, the recovery of local threatened and endangered species which have struggled to gain a foothold for decades.”

 

Montanore is an advanced stage exploration project; the deposit contains 81.5 million tons with average grades of 2.04 oz silver per ton and 0.74% copper. With publication of the final EIS and draft RoD, the project enters the final phase of agency authorization. Upon issuance of the final RoD by the USFS and Montana Department of Environmental Quality, the company will be authorized to commence activities for the project to prepare a bankable feasibility study for financing the capital construction of the mine.

Imperial Metals Starts Up at Red Chris Copper Mine in BC

Imperial Metals' Red Chris mine is scheduled to produce, on average, 123,000 mt/y of 27% copper concentrates over a mine life of just over 28 years. (Photo courtesy of Imperial Metals)

 

Imperial Metals began commissioning the mill and concentrator at its new Red Chris copper mine in northwest British Columbia in early February and trucked its first shipments of copper concentrate to the Port of Stewart, British Columbia, on February 27. The plant processed a little more than 193,000 metric tons (mt) in February and produced approximately 2,400 mt of copper concentrate. The plant has a designed throughput capacity of 30,000 mt/d.

 

Commissioning of the Red Chris flotation circuit with low-grade ore began on February 15. During the second week of startup, the mill feed grade was increased using ores from both the East and Main zones of the mine. The plant’s first full 12-hour operating shift without stoppage took place on February 22. The plant milled approximately 15,500 mt during the 12-hour period.

 

Red Chris process plantRed Chris is scheduled to produce an average of 123,000 mt/y of 27% copper concentrate over a mine life of 28.3 years. The mine’s production fleet includes a P&H 2800 electric cable shovel and CAT 793 haul trucks. Mining is initially from the East and Main zone pits, which will eventually form one large pit.

 

The company said that, as of early March, the Red Chris commissioning team was focused on achieving continuous operations and a consistent final concentrate grade. When satisfied with progress in these areas, they will place more emphasis on metal recoveries and throughput.

 

Imperial’s wholly owned Red Chris property is located 80 km south of the town of Dease Lake in northwest British Columbia. The property covers a total area of 29,482 ha, comprising five 30-year mining leases covering 5,141 ha and 83 mineral claims encompassing 24,341 ha.

Dynacor Receives Construction Permit for New Gold Mill in Peru

Dynacor Gold Mines has received the construction permit for its planned new custom gold ore processing plant in Chala, southern Peru. The Chala plant will have an initial ore processing capacity of 300 mt/d (102,000 mt/y) and has been designed to be readily expanded to 450 mt/d (153,000 mt/y) and then to 600 mt/d (204,000 mt/y) by adding additional processing lines and ball mills.

 

The plant will process ore purchased from small Peruvian mining companies.

 

Dynacor is a Canadian company headquartered in Montreal, Quebec. It currently operates an 85,000-mt/y gold ore processing plant in Huanca, Peru, which also processes purchased ore. The Huanca plant poured its first gold in 1998.

 

The Chala facility will be built on a 135-ha site that is part of a 200-ha mining concession that Dynacor purchased in March 2011. The concession is located in the department of Arequipa, district of Chala, in the heart of one of the most productive gold mining regions of Peru. The total construction cost is estimated at $10 million and will be financed internally.

 

The construction permit was issued by Peru’s Ministry of Energy and Mines.

 

Work already completed at the Chala site includes: a 5-km road connecting the site to the Pan-American South highway; a power line connected to the national power grid; water wells, water storage tanks and a pumping station; a perimeter security fence and gate; housing facilities for the company’s employees and construction crews; and milling equipment, including two 7- x 8-ft ball mills that were tested at the Huanca mill. The site has ample space for tailings ponds for many years of operation.

Yamana Gives Go-ahead for High-grade Cerro Moro Mine, Argentina

Yamana Gold announced in mid-February that it will proceed with construction of its high-grade, low-cost Cerro Moro gold-silver project in Santa Cruz province, southern Argentina. Planning calls for average annual production of 135,000 oz of gold and 6.7 million oz of silver during the first three years of full production. Production over the currently planned mine life of about eight years will average 102,000 oz/y of gold and 5 million oz/y of silver.

 

These life-of-mine production estimates consider only current mineral reserves. Yamana anticipates that the project will benefit from additions to reserves through exploration and new discoveries.

 

Plant throughput is planned at 1,000 mt/d, with head grades averaging 10.8 g/mt gold and 536 g/mt silver.

 

Yamana released a feasibility study of the Cerro Moro project in April 2014 that called for two stages of development. However, the company has now decided to pursue a single-stage development scenario.

 

Cash costs of production are estimated at $380 to $400/oz for gold and $5.35 to $5.50/oz for silver, and all in sustaining costs are estimated at $547 to $557/oz for gold and $7.60 to $7.80/oz for silver. Total life-of-mine project capital is estimated at $398 million, including $265 million in initial capital and $133 million for life-of-mine sustaining capital.

 

Cerro Moro project capital spending in 2015 is expected to total about $30 million, with more than half of the spending to occur late in the year when formal construction groundbreaking is scheduled to take place. The remaining capital will be spent in 2016 and 2017. Production is expected to begin in the second half of 2017.

 

Cerro Moro mine production will be from a series of small open pits and from underground mines on veins.

Endeavour Silver Increasing Production at El Cubo, Mexico

Endeavour plans to invest $36.5 million on capital projects for its El Cubo mine in 2015.

 

Endeavour Silver is increasing production at its El Cubo silver mine in Guanajuato state, Mexico, from 1,550 metric tons per day (mt/d) to 2,200 mt/d, with expectations that the expansion will be complete by July. The additional 650 mt/d of mine production will come primarily from the V-Asunción mine area, which has thicker mineralized zones amenable to long hole mining, and the Santa Cecilia mine area, which has narrower but higher-grade veins.

 

The added production will be processed at Endeavour’s Bolañitos plant, 18 km from El Cubo. The Bolañitos plant has available capacity and comparable circuits to the plant at El Cubo. Production at Bolañitos will be reduced by a small amount to accommodate processing of more El Cubo ore.

 

“The main reason for the mine expansion is to drive operating costs lower and generate free cash flow at El Cubo by taking advantage of the available plant capacity at Bolañitos,” the Endeavour announcement said. “As a result, El Cubo will become the company’s largest mine by metal production. Endeavour received the cooperation of the miners’ union at El Cubo in finalizing a labor contract that facilitates the mine expansion and helps establish the short- and long-term viability of the mine.”

 

Endeavour has three mines in Mexico: El Cubo, Bolañitos and Guanacevi. With increased production from El Cubo, the company is now forecasting 2015 production of 6.3 million to 7 million oz of silver and 60,000 to 66,000 oz of gold. Consolidated cash costs on a co-product basis are expected to come in around $13 to $14/oz for silver and $900 to $975/oz for gold.

 

Endeavour plans to invest $36.5 million on capital projects in 2015. The total includes $30 million for mine development, infrastructure and exploration; $4.3 million for plant infrastructure, equipment and tailings; and $2.2 million for miscellaneous items. The mine development capital is for accessing reserves and converting resources into reserves.

 

Endeavour Silver CEO Bradford Cook said, “We fulfilled our initial two-year capital expansion and operating turn-around plans at El Cubo in December 2014, but with precious metal prices still falling, it was clear we needed to do more to make El Cubo a viable mine. The current mine expansion will bring operating costs down further and should allow El Cubo to start generating free cash flow.”

Outotec to Deliver Modular SX Technology to South America

Outotec has won an order for the delivery of its VSFX modular solvent extraction (SX) technology and services to a brownfield copper production plant in South America. The customer is making changes to their heap leaching operation to enhance the copper recovery from secondary sulfide minerals. These changes in the leaching phase require an upgrade in the downstream SX plant washing capacity.

 

“This order demonstrates how Outotec’s revolutionary modular plant concept provides added value in projects,” said Robin Lindahl, head of the metals, energy and water business area at Outotec. “Modular technology enables quick delivery and installation, safe operation as well as high performance and availability even during maintenance, all backed up by performance guarantees. With our solution the customer can reach the targeted production in the planned fast schedule, safely and with minimal construction work at the site. The technology fulfills the strictest environmental and safety standards, minimizes the energy consumption and reduces the overall project risks.”

 

Outotec has developed the highly acclaimed VSFX technology in the last few years and launched the technology at the end of 2013. There is an increasing demand for this concept in various solvent extraction applications, both in brownfield optimization projects and greenfield plants.

EMEA

Boliden Expanding in Norway; Pursuing New Nickel Strategy for Finland

On November 10, Boliden announced plans to expand zinc production at its smelter in Odda, Norway, and a change of business strategy from tolling to purchasing nickel concentrates for processing at its Harjavalta, Finland, copper-nickel smelter.

 

At Odda, Boliden is investing 350 million Norwegian krone (about $52 million) to increase production of zinc metal from 170,000 to 200,000 metric tons per year (mt/y). The plant is expected to achieve the new capacity in the latter half of 2017.

 

About 80% of the zinc concentrates processed at Odda come from Boliden mines in Sweden and Ireland, the rest from mines in Canada and Peru. About 93% of the zinc metal produced is exported to steel mills in Europe, Scandinavia and Britain for use in producing galvanized steel.

 

At Harjavalta, Boliden is launching an independent nickel smelting business, buying nickel concentrates from external suppliers and selling nickel matte to nickel refineries. For several years, the Harjavalta plant has been tolling nickel concentrates owned by external parties for a fee. In 2013, Harjavalta processed approximately 250,000 mt of nickel concentrates into nickel matte, containing about 25,000 mt of nickel, for further treatment at external nickel refineries.

 

Under the new business plan, Boliden expects production to remain at 25,000 mt/y of nickel in matte. Boliden will buy concentrates from a variety of mines and sell the nickel matte to nickel refineries.

 

At Garpenberg, Boliden recently completed an expansion of mine production from 1.4 million to 2.5 million mt/y. The expansion program started in 2011 and included construction of a new concentrator, new shafts and underground facilities, and infrastructure upgrades. Capital investment totaled 3.9 billion Swedish kronor (about $560 million).

 

The Garpenberg mine produces complex ores containing zinc, lead, silver, copper and gold. The concentrator produces zinc, lead and copper concentrates. The zinc and lead concentrates are transported by truck to Gävle port for onward transport by ship, mainly to Boliden smelters in Rönnskär, Sweden; Kokkola, Finland; and Odda, Norway. The copper concentrate is trucked to a rail loading station for onward rail transport to the Rönnskär smelter.

 

Underground, automated and remotely controlled loading and haulage at Garpenberg are now based on Sandvik's "AutoMine" system. Ventilation in the mine is also automated and runs on an on-demand basis, saving on energy needed to run the fans and provide heating. Water consumption/mt of ore produced has been reduced through more efficient management and updated equipment. Advanced nitrogen and water purification systems will also help ensure that there is no increase in the mine's environmental impact.

Work on Rio Tinto’s Spain Copper Project to Begin this Year

EMED Mining recently provided an update for its Rio Tinto copper project in Spain.

 

“We recently had a series of meetings between our board of directors and the representatives of the Andalucian Government who oversee the regulatory process for our Rio Tinto Copper Project,” said Harry Anagnostaras-Adams, managing director and CEO for EMED Mining. “We are pleased to have satisfactorily discussed the proposed conditions of approval and the process for formalizing permission to start the project works. It seems that all key stakeholders are working to allow works to be triggered in the second half of 2013.”

 

EMED maintains the target date of the end of 2015 for establishing initial base case production of 37,000 metric tons per year (mt/y) copper-in-concentrate, with construction starting during the second half of 2013 and production beginning in the second half of 2014.

Russia’s Alrosa Launches Mining on the Botuobinskaya Pipe

Russian diamond producer Alrosa has started mining ore from the Botuobinskaya kimberlite pipe at its Nyurba Mining and Processing Division (Nyurba MPD) in the Republic of Sahka (Yakutia) in Russia’s Far East. The pipe is expected to produce 230,000 metric tons (mt) of ore and about 1 million carats of rough diamonds in 2015. When the mine reaches its design capacity of 400,000 mt/y of ore, its diamond production will exceed 2 million carats/y.

 

Botuobinskaya has been developed as an open-pit mine. Stripping operations began in 2013. Ore processing takes place at existing Nyurba MPD processing facilities.

 

Botuobinskaya is located in the Nakyn ore field, 3 km from the Nyurbinskaya pipe, the main deposit of the Nyurba MPD. The launch of mining at Botuobinskaya will compensate for a decrease in production from the Nyurbinskaya pipe and allow Nyurba MPD to maintain stable production volumes at 7.5 million carats/y of rough diamonds.

 

According to the Russian ore reserves classification system, reserves of rough diamonds at Botuobinskaya totaled 93.021 million carats at an average diamond grade of 5.65 carats/mt as of January 1. Indicated resources totaled 70.994 million carats an average grade of 5.19 carats/mt. Under JORC standards, the reserves totaled 71.044 million carats.

 

The pipe’s diamonds are characterized by a relatively large proportion of gem-quality and near-gem-quality crystals with a high degree of transparency.

 

At the official Botuobinskaya opening ceremony, acting Alrosa President Ilya Ryashchin said, “Over the past few years, Alrosa has invested significant funds in building new production capacities. The newly commissioned Botuobinskaya pipe is the first new pipe in Yakutia over the last 10 years. The development of this deposit is included in Alrosa’s long-term development strategy, which envisages an increase of diamond production to 41 million carats/y through putting new pipes into operation.”

 

Alrosa’s 2014 diamond production totaled 36.2 million carats.

Roxgold Clears Permitting for Yaramoko Gold Project 

Roxgold Inc. received the exploitation permit for its Yaramoko gold project in Burkina Faso in late January and was expecting to begin initial site work shortly thereafter. The exploitation permit was finalized through endorsement of a Mining Decree by the president of Burkina Faso and other governmental authorities. The decree formally grants Roxgold the rights to develop and operate the Yaramoko project.

 

The Yaramoko project is located in the Houndé greenstone region of Burkina Faso, approximately 200 km southwest of the capital city of Ouagadougou. The property is directly south of and contiguous to Semafo’s Mana gold mine property.

 

Roxgold released the results of the Yaramoko feasibility study in April 2014. Probable mineral reserves stand at just under 2 million metric tons (mt), grading 11.8 g/mt gold and containing 759,000 oz of gold. The feasibility study envisions an underground mining operation producing an average of 99,500 oz/y of gold over an initial mine life of 7.4 years.

 

Pre-production capital costs are estimated at $106.5 million. Average all-in sustaining costs are estimated at $590/oz.

 

The upper levels of the Yaramoko mine will be accessed through two spiral declines. At the 5072 level, approximately 240 m below surface, the double decline access ends, and a single decline progresses from this level to the 4884 level, 430 m below surface. Twenty-four levels of lateral development designed to openup multiple working faces and allow operating flexibility are incorporated into the mine plan.

 

Mining will be based on long-hole retreat mining on close-spaced sublevels, with cemented rock backfill used to eliminate nonrecoverable pillars, maximizing mining recovery to 96%. The feasibility study assumes initial contractor mining, with engineering and grade control provided by Roxgold. Owner mining is assumed after approximately five years of operation.

 

The mine plan is based on a 4.9-g/mt gold cutoff at a minimum mining width of 1.6 m. A 750-mt/d extraction rate is planned. The typical stope has a 25-m strike length, a vertical height of 34 m, and full-vein width. The average vein width before dilution is 4 m.

 

The processing facility will be sized for 750-mt/d throughput. The flowsheet includes single-stage jaw crushing, SAG milling, gravity recovery, leaching and adsorption circuits, gold recovery, and thickening. Average recoveries are assumed to be 96.9% based on three rounds of metallurgical test work. Material milled is estimated to be of moderate hardness with a Bond Ball Work Index of 18 kWh/mt.

 

The plant will be amenable to expansion at minimum additional investment in the event that extraction under the current mine plan is higher than forecast or additional sources of ore feed are developed.

 

ASIA

Indian Coal Imports Could Surge This Year

Reuters reported that Anil Swarup, coal secretary for India, said, as power companies add capacity to meet rising demand even as millions go without electricity, India’s coal imports are expected to jump 19% to a record of about 200 million metric tons (mt) this fiscal year. He said shipments into the world’s third-largest coal importer are, however, likely to slide back to about 160 million mt next year, starting April 1, as state-run Coal India Ltd. (CIL) and private companies ramp up output.

 

India, which buys most of its coal from Indonesia, Australia and South Africa, is targeting to stop imports of power-generating thermal coal in the next few years, though purchases of high-grade steelmaking coal will continue.

 

He said that CIL, the world’s largest coal miner, is expected to boost output by 50 million mt in 2015-2016 to 550 million mt. The government has set it a target of 1 billion mt by 2019-2020. Coal demand was estimated at 787 million mt for this fiscal year and is going to jump in the next few years, driven by Prime Minister Narendra Modi’s promise to supply power to all. About 280 million people in 56 million homes, or about a fourth of India’s 1.2 billion people, still go without electricity, even though coal-fired power generation has been rising steadily.

India’s Largest Manganese Producer to Expand Production

India’s MOIL Ltd. (formerly Manganese Ore India Ltd.) will double its manganese production from the current level of 1.13 million mt/y by adding mineable land and upgrading existing operations to meet a predicted shortage of the metal in the country.

 

MOIL, which accounts for 65% of India’s manganese production, has been granted prospecting licenses on 597 hectares in the western state of Maharashtra, in close proximity to the miner’s existing 11 mines in the region, a company official said, noting that with the additional acreage, along with startup of a new production shaft at a nearby mine, MOIL would be able to double its production over the next three to four years.

 

The expansion plans of MOIL comes in wake of warnings of a severe shortage of manganese in the domestic market raised by the Indian Bureau of Mines (IBM), the government’s multidisciplinary body overseeing the mineral sector. According to a report prepared by IBM, given the total combined production of manganese by companies such as MOIL, Tata, Orissa Mining Corp. (OMC) and Sandur, including current and future expansion projects, the country’s domestic supply of manganese would not exceed 5 million mt/y compared with total projected demand of 9 million mt/y by 2020 from the domestic steel industry.

 

The report stated that at a consumption rate of 9 million mt/y run-of-mine (ROM) manganese ore, India’s current estimated reserves of 142 million mt would last only 10–15 years beyond 2020. And with no secondary supply of the metal through recycling, additional metal would have to be made available through imports unless domestic mining dynamics were changed.

 

With high-grade manganese ore reserves dwindling and revision of the threshold value of manganese ore to 10% metal content, the mining industry is obliged to exploit lower-grade manganese ore that is now considered waste, the IBM report concluded.

Chinese Coal Industry Steps Into Production Control

China’s Shanxi province recently released its energy development strategic objectives for the next five years, which identified its goals on coal, according to China Daily. The strategic objectives said coal output will be controlled within the limit of 1 billion metric tons (mt) by 2020. Outbound coal will be controlled within the limit of 600 million mt, and the province’s energy consumption will be around 260 million mt of standard coal.

 

Also, Shenhua Group, China’s largest coal producer, will reduce output by 10.8% this year or 33 million mt of coal compared to 2014. Other coal giants like China Coal Energy and Datong Coal Mine Group also put out production limit plans.

 

Chinese coal production growth, which has already lasted 14 years, ended in 2014. According to the National Bureau of Statistics, in the past year, national raw coal output was 3.87 billion mt, down 2.5% year-on-year.

AUSTRALIA/ OCEANIA

Australian Major Mining Construction Projects

The Australian Bureau of Resources and Energy Economics (BREE) publishes a detailed list of mining construction projects currently under development. It also lists projects that are less advanced. The information is broken down by state and details. Click here for the entire list.

Sirius Starts Construction of Nova Nickel Mine

Nova mineralization is in the form of a magmatic nickel sulphide deposit.

 

Sirius Resources reported in late January that construction is under way at its 100% owned, underground Nova nickel mine near Norseman, Western Australia. Project development is based on a definitive feasibility study released in July 2014. At full production, the mine is expected to produce an average of 26,000 metric tons per year (mt/y) of nickel and 850 mt/y of cobalt in a nickel concentrate and 11,500 mt/y of copper in a separate copper concentrate.

 

First concentrate production is planned for the fourth quarter of 2016. Mill throughput at design capacity will be 1.5 million mt/y. Initial mine life is planned at 10 years. Capital cost to develop the project is estimated at A$443 million.

 

Nova mine development is being undertaken by underground mining contractor Barminco under a three-year contract valued at A$129 million. A boxcut is being opened to provide access to fresh rock for driving of a decline to access the mine. The contract includes initial mining of the Nova orebody.

 

The Nova deposit is a magmatic nickel sulphide deposit. The initial probable ore reserve totals 13.1 million mt grading 2.1% nickel, 0.9% copper, and 0.07% cobalt, containing 273,000 mt of nickel, 112,000 mt of copper, and 9,000 mt of cobalt.

 

Approximately 83% of the planned production will be from sublevel open stoping, with the remaining 17% produced from longhole echelon retreat stoping. Ore and waste will be hauled in 60-mt underground trucks up a straight, one-in-seven gradient decline. The decline has been designed to allow conveyor haulage to be retrofitted at a later date if deemed appropriate.

 

The processing plant will utilize a conventional crushing process, with a primary crusher fed from stockpiles by a dedicated front-end loader. Grinding by an open-circuit SAG mill will be followed by a ball mill in closed circuit with hydrocyclones. Flotation will be through roughing, cleaning, and cleaner scavenging open circuits, which will be replicated for copper and nickel. Regrinding on particular streams will be used to increase liberation and recovery for both circuits.

 

The Nova exploration camp is being expanded and converted to become a 200-person temporary construction camp to house the workforce while the permanent accommodation village is being built. The permanent accommodation village is scheduled for completion in August.

 

Kintyre Uranium Project Receives Conditional Environmental Approval

Cameco reported in early March that Western Australia’s minister for environment, Albert Jacob, conditionally approved Cameco and Mitsubishi Development’s Kintyre uranium project in the remote East Pilbara region of Western Australia. Cameco owns 70% of the project and is the operator; Mitsubish owns the remaining 30%.

 

Cameco Australia Managing Director Brian Reilly welcomed the approval, which followed a high-level environmental impact assessment and more than four years of extensive community consultation and rigorous environmental and technical studies. He also said that, while Cameco is continuing to take steps to develop its Australian projects, no development decisions will be made until market conditions signal new uranium production is required.

 

“For Kintyre, this means advancing the project through the environmental assessment process, continuing to build strong relationships with stakeholders, and identifying additional resources to improve the economics of the project,” Reilly said.

 

The Kintyre project is located 60 km south of Telfer and 260 km northeast of Newman at the western edge of the Great Sandy Desert in the East Pilbara region. Measured and indicated mineral resources are estimated at about 55 million lb of U3O8 at an average grade of 0.58% U3O8. A 2012 prefeasibility study suggested that the open-pit project might produce about 6 million lb/y of U3O8 over a mine life of seven years. However, the study concluded that to break even, the project would require higher uranium prices or greater total production.

 

A decision from Australia’s federal Minister for the Environment regarding the Kintyre project is pending.

 

McIlvaine Company

Northfield, IL 60093-2743

Tel:  847-784-0012; Fax:  847-784-0061

E-mail:  editor@mcilvainecompany.com

Web site:  www.mcilvainecompany.com