Figure IV-1. Forced Oxidation System Total Capital Requirement
(300 MW, 2.6% S Coal) (Dollars)
| Description | $/kW |
| Reagent Feed System | 28.8 |
| SO2 Removal System | 55.9 |
| Flue Gas Handling System | 18.6 |
| Solids Handling System | 5.2 |
| General Support Equipment | 1.5 |
| Additional Equipment | 3.1 |
| Total Process Capital |
113.2 |
| General Facilities | 11.3 |
| Engineering and Home Office Fees | 11.3 |
| Project Contingency | 19.7 |
| Process Contingency |
2.7 |
| Total Plant Cost (TPC) | 158.2 |
| Total Cash Expended (TCE) | 154.5 |
| Allowance for Funds During Construction (AFDC) |
8.6 |
| Total Plant Investment (TPI) | 163.1 |
| Royalty Allowance | 0.6 |
| Preproduction Cost | 5.7 |
| Inventory Capital | 0.7 |
| Initial Catalyst and Chemicals |
0 |
| Total Capital Requirement (TCR-New Plant) | 170.1 |
| Total Capital Requirement (TCR-Moderate Retrofit) | 216.2 |