Figure IV-1. Forced Oxidation System Total Capital Requirement
(300 MW, 2.6% S Coal) (Dollars)

Description $/kW
Reagent Feed System 28.8
SO2 Removal System 55.9
Flue Gas Handling System 18.6
Solids Handling System 5.2
General Support Equipment 1.5
Additional Equipment 3.1
Total Process Capital

113.2

General Facilities 11.3
Engineering and Home Office Fees 11.3
Project Contingency 19.7
Process Contingency

2.7

         Total Plant Cost (TPC) 158.2
         Total Cash Expended (TCE) 154.5
Allowance for Funds During Construction (AFDC)

8.6

         Total Plant Investment (TPI) 163.1
Royalty Allowance 0.6
Preproduction Cost 5.7
Inventory Capital 0.7
Initial Catalyst and Chemicals

0

        Total Capital Requirement (TCR-New Plant) 170.1
        Total Capital Requirement (TCR-Moderate Retrofit) 216.2