Figure IV-1. Forced Oxidation System Total Capital Requirement
(300 MW, 2.6% S Coal) (Dollars)
Description | $/kW |
Reagent Feed System | 28.8 |
SO2 Removal System | 55.9 |
Flue Gas Handling System | 18.6 |
Solids Handling System | 5.2 |
General Support Equipment | 1.5 |
Additional Equipment | 3.1 |
Total Process Capital |
113.2 |
General Facilities | 11.3 |
Engineering and Home Office Fees | 11.3 |
Project Contingency | 19.7 |
Process Contingency |
2.7 |
Total Plant Cost (TPC) | 158.2 |
Total Cash Expended (TCE) | 154.5 |
Allowance for Funds During Construction (AFDC) |
8.6 |
Total Plant Investment (TPI) | 163.1 |
Royalty Allowance | 0.6 |
Preproduction Cost | 5.7 |
Inventory Capital | 0.7 |
Initial Catalyst and Chemicals |
0 |
Total Capital Requirement (TCR-New Plant) | 170.1 |
Total Capital Requirement (TCR-Moderate Retrofit) | 216.2 |