Major FGD Project Schedule Changes with Bush Re-election

 

The Bush re-election makes it unlikely that there will be many expedited FGD projects based on NSR litigation. In McIlvaine’s Utility Upgrade Tracking Systems there is an estimated FGD start date for more than 300 units. Many of the start dates are based on information received directly from the utilities or from suppliers who have orders or are bidding components or systems for specific start dates.

We also have estimated start dates based on the assumption that the average utility system will not rely on buying significant allowances but will achieve reductions through scrubbing.  Some of these units were estimated for 2007 and 2008 start dates even though no apparent activity had commenced.  Now with the possibility of an aggressive new program eliminated with the Bush re-election, it is very unlikely that these systems will be installed in this timeframe.

We have, therefore, moved the start dates for this category of systems to 2010.  We did this despite the realization that bunching a large number of startups into one year is unrealistic. Therefore, a number of these dates will change again in the coming months. Ultimately 100,000 MW of scrubbers will be needed to meet the CAIR limits.  The allowance bank, however, will provide some opportunity to delay installation a few years beyond 2010.

On the other hand, here is still a good case to be made that more units will start up in 2008 than are listed.  In fact, we have confidential information on some which are not posted. More than one utility is trying to move up its start dates to take advantage of the SO2 allowance prices.

This week SO2 allowance prices rose to over $600/ton. The high price of natural gas has led to greater use of coal than anticipated. There are also circumstances which will prevent allowances from being available.  States which are mandating scrubbers are restricting the sale of allowances from those plants. These factors will lead to maintenance of high allowance prices, followed by scrubber installations to take advantage of those high prices. Ultimately, the price of allowances will come down to the marginal cost of scrubbing which averages close to $400/ton.

 

EPA estimates that the cost of either allowances or scrubbing will be $600/ton in 2008 and rise to $1,000/ton in 2015.  This is because the cost of scrubbing is a function of the SO2 content, site, physical limits, and other factors.  The assumption that costs will vary greatly from unit to unit are being verified by recent experience.

 

For more information on a system which provides all the plant by plant forecasts of both FGD and SCR projects click on:  Utility Environmental Upgrade Tracking System http://www.mcilvainecompany.com/energy.html .

 

 

 

Bob McIlvaine

847-784-0012

www.mcilvainecompany.com