World Power Generation Projects

Project Title

     First Entry Date: 8/1/2004
     Revision Date: 5/1/2005

                 Location: OH   could also be built in IN, KY, VA,or WV
                 Startup Date: 2010
                 Size: 600  MW (could by 1200)
                 Primary Fuel: Coal Gas    
                 Secondary Fuel:  
                 Duct Burner:      
                 Duct Burner Supplier:  
                 Oxidation Catalyst:      
                 Oxidation Catalyst Supplier:
  
                 NOx Limit:             
                 CO Limit:
  
                 VOC Limit:             
                 PM limit:
  
                 SO2 Limit:              
                 NH3 limit:  

          Description:
         
 AEP wants assurances on cost recovery wherever it builds this plant. Location decision could be made by June 2005. Having interconnection evaluated for three sites--Mason County, WV; Meigs County, OH; and Lewis County, KY. Filed initial Public Service Commission notices for 600 MW plant. PSC decision expected in August.


Contractor 

Contractor Comment

General Electric scoping study, IGCC equipment
Bechtel scoping study
NOx Control Type Supplier
No NOx control information available.