World Power Generation Projects
| Project Title |
First Entry Date: 9/1/2000
Revision Date: 7/1/2005
Location: WI
Startup Date: 2005
Size: 545 MW
Primary Fuel: Gas
Secondary Fuel:
Duct Burner: y
Duct Burner Supplier:
Oxidation Catalyst: y
Oxidation Catalyst Supplier:
NOx Limit:
CO Limit:
VOC Limit:
PM limit:
SO2 Limit:
NH3 limit:
Description:
The Public Service Commission of Wisconsin approved the project.
12/02 Washington Group received a limited notice to proceed on first 545 MW
unit. Second unit may be built by 2008. Groundbreaking 6/03 A court ruled that
the WI Public Service Commission failed to make an adequate analysis of the
environmental impact of the new plant. However construction does not have to
stop. State regulators say an in-depth environmental review is not needed for
this project. 3/04 In operation. 7/05
|
Contractor |
Contractor Comment |
| Alstom | HRSG |
| Washington Group | EPC contractor |
| General Electric | turbines |
| NOx Control Type | Supplier |
| SCR |