World Power Generation Projects

Project Title:

     First Entry Date: 1/1/2005
     Revision Date: 1/1/2009

                 Location: WY   near Gillette
                 Startup Date: 2011
                 Size: 385  MW
                 Primary Fuel: Coal   PRB
                 Secondary Fuel:  
                 Duct Burner:      
                 Duct Burner Supplier:  
                 Oxidation Catalyst:      
                 Oxidation Catalyst Supplier:
  
                 NOx Limit:             
                 CO Limit:
  
                 VOC Limit:             
                 PM limit:
  
                 SO2 Limit:              
                 NH3 limit:  

          Description:
         
 Mine mouth project. Company still evaluating technology, but is considering a 2006 construction start date. 6/05 Developing application for an air quality permit. 11/05 Upped MW by 25 and seeking federal financing through the Rural Utilities Services program. Hearings for permit 5/06 Construction expected to begin in 2007. 3/07 Sierra Club actively opposes. Hearings run to end of March 2007. 10/07 Issued emissions permit. 11/07 Groundbreaking. Environmental groups asking state officials to revoke permit. Will feature B&W AireJet burner. 12/07 Graf-Wulff designed circulating fluid bed FGD system, Nooter Construction construction 1/09 Emerson Process Management will digitally automate.


 Contractor 

 Contractor Comment

 Babcock & Wilcox  boiler and SCR
 Mitsubishi  turbine generator
 Sargent & Lundy  engineering
 NOx Control Type  Supplier
No NOx control information available.