Title: Gas Turbine Combined Cycle Fast Start: The Physics Behind the Concept

GTCC startup optimization is essentially minimizing the time required to reach the dispatch power (e.g., full load or a specific part load) without "breaking anything" in the process. For example, failure to control thermal stresses results in cracks via low/high cycle fatigue (LCF and HCF) and brittle fracture. This article provide relevant and easy-to-use technical information (in the form of simple charts, basic equations and representative physical quantities) to form an informed opinion on available technologies for GTCC startups.

Click Here For Complete Article Text

 